Meaning of quantum meruit
Quantum meruit is a Latin term meaning ‘the amount deserved’ or ‘what the job is worth’. It is used to refer to a claim for a reasonable sum, such as when a contractor seeks payment for work which has not been determined by a contract. If there is a contract that entitles one party to receive an agreed or reasonable sum from the other then the law of contract applies and a claim for quantum meruit cannot be used.
A claim may arise in circumstances, including:
- Where there is a quasi-contract (e.g. where some contractual terms have been agreed but price has not).
- Where no price has been fixed.
- Where there is work done that falls outside the contract.
- Where there is work done under a void or unenforceable contract.
The contractor must demonstrate that the employer requested, either expressly or impliedly, the work to be done, or freely accepted it. However, in practice, it can prove difficult for the contractor to prove the exact amount of their entitlement under the principle of quantum meruit.
There are no stipulations as to how the reasonable sum is to be assessed as circumstances often differ. The assessment of a claim for quantum meruit in the absence of a contract will differ from the assessment of a reasonable sum to be paid within a contractual framework. Where work done outside an existing contract gives rise to a quantum meruit claim, the contractor should be paid at a fair commercial rate rather than as though it had been performed under the contract (which may be a different rate).
Evidence that can prove useful to a claim includes:
- Any abortive negotiations relating to price.
- The prices in a related contract.
- Calculations based on the net cost of labour and materials.
- Expert opinions regarding what constitutes a reasonable sum.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Contract conditions.
- Contract law.
- Contract sum.
- Defined cost.
- Difference between lump sum and measurement contracts.
- Disallowed cost.
- Glossary of property law terms.
- Letter of intent.
- Loss and expense.
- Payment for extra work.
- Remeasurement.
- Retention.
- Right to payment.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
New Great British Energy partnership launched
Crown estate help to turbocharge energy independence.
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.